Basic tariffs for design and construction works
For one-time jobs
No. Types of work and costs Units of measurement Minimum unit for calculations Price including VAT, rubles
1. DESIGN WORK
1.1. Development and approval of working projects for laying communication lines (including pre-design survey of the route without a team visit) 1 km 1 km 20 000
1.2. Development of a sketch for laying a communication line 1 km 1 km 10 000
1.3. Additional work on the development and approval of a project for laying communication lines through buildings and structures (including automatic telephone exchanges) 1 object 1 object 7 000
1.4. Additional work to obtain technical specifications and approve the project in the collectors and bridges of JSC Moskollektor, State Unitary Enterprise Gormost and other owners 1 object 1 object 5 000
1.5. Preparation and approval of a detailed design for the construction of a telephone sewer system (including obtaining and approval of a geological basis) 100 m 100 m Negotiable
1.6. Preparation and approval of permitting documentation for the construction and/or restoration of telephone sewer systems 1 day 1 day Negotiable
2. CONSTRUCTION AND INSTALLATION WORKS. LAYING AND INSTALLATION OF FIBER OPTIC COMMUNICATION CABLES IN EXISTING CABLE STRUCTURES
2.1. Laying and installation of 8-fiber optical cable (including cable cost) 1 km 0.5 km 125 000
2.2. Laying and installation of an 8-fiber optical cable in a flame-retardant sheath during group installation (including the cost of the cable) 1 km 0.5 km 139 000
2.3. Laying and installation of 16-fiber optical cable (including cable cost) 1 km 0.5 km 135 000
2.4. Laying and installation of a 16-fiber optical cable in a flame-retardant sheath during group installation (including the cost of the cable) 1 km 0.5 km 149 000
2.5. Laying and installation of 24-fiber optical cable (including cable cost) 1 km 0.5 km 150 000
2.6. Laying and installation of a 24-fiber optical cable in a flame-retardant sheath during group installation (including the cost of the cable) 1 km 0.5 km 165 000
2.7. Laying and installation of 32-fiber optical cable (including cable cost) 1 km 0.5 km 160 000
2.8. Laying and installation of a 32-fiber optical cable in a flame retardant sheath during group installation (including the cost of the cable) 1 km 0.5 km 174 000
2.9. Laying and installation of a 48-fiber optical cable (including the cost of the cable) 1 km 0.5 km 178 000
2.10. Laying and installation of a 48-fiber optical cable in a flame-retardant sheath during group installation (including the cost of the cable) 1 km 0.5 km 192 000
2.11. Laying and installation of a 64-fiber optical cable (including the cost of the cable) 1 km 0.5 km 210 000
2.12. Laying and installation of a 64-fiber optical cable in a flame-retardant sheath during group installation (including the cost of the cable) 1 km 0.5 km 226 000
2.13. Laying and installation of 96-fiber optical cable (including cable cost) 1 km 0.5 km 260 000
2.14. Laying and installation of a 96-fiber optical cable in a flame-retardant sheath during group installation (including the cost of the cable) 1 km 0.5 km 276 000
2.15. Laying and installation of 144-fiber optical cable (including cable cost) 1 km 0.5 km 320 000
2.16. Laying and installation of a 144-fiber optical cable in a flame-retardant sheath during group installation (including the cost of the cable) 1 km 0.5 km 336 000
2.17. Laying and installation of 288 fiber optical cable (including cable cost) 1 km 0.5 km 560 000
2.18. Laying and installation of a 288-fiber optical cable in a flame-retardant sheath during group installation (including the cost of the cable) 1 km 0.5 km 580 000
2.19. Installation and reinstallation of an additional coupling along the fiber-optic cable route pcs. 1 piece 10 000
2.20. Additional work on optical fiber welding 1 fiber 8 fibers 360
2.21. Coupling re-assembly (up to 32 welded joints) 1 coupling 1 coupling 20 000
2.22. Carrying out a set of control measurements 1 fiber 12 fibers 410

The minimum construction length of cable laying is 0.5 km

The minimum construction length of cable laying in a building is considered to be 100.0 m

3. CONSTRUCTION AND INSTALLATION WORKS ON DEVELOPMENT, CONSTRUCTION AND/OR RESTORATION OF TELEPHONE SEWER, DEVICE OF TELEPHONE INPUT INTO BUILDINGS, INSTALLATION OF WELLS
3.1. Report, construction and/or restoration of telephone sewerage with the number of channels from 1 to 2 1 p.m. 10 p.m. 4 200
3.2. Installation of reinforced concrete telephone wells KKS-1, including their cost 1 piece 1 piece 70 000
3.3. Installation of reinforced concrete telephone wells KKS-2, including their cost 1 piece 1 piece 90 000
3.4. Raising and restoring the neck of a telephone well on the lawn 1 piece 1 piece 15 000
3.5. Raising and restoring the neck of a telephone well on a road or sidewalk 1 piece 1 piece 22 000
3.6. Asphalting taking into account the cost of materials 1 m 1 m 2 000
3.7. Construction (restoration) of the "Leningrad" input 1 piece 1 piece 20 000
3.8. Construction of a new entrance to the building 1 piece 1 piece 22 000
3.9. Pumping water from a telephone well 1 piece 1 piece 3 000
4. OTHER WORK RELATED TO CABLE LAYING
4.1. Fire protection of fiber-optic communication cables in the collectors of Moskollektor JSC (with materials) 1 km 0.25 km 45 000
4.2. Preliminary inspection of the loading of TV channels along the proposed cable laying routes with pulling of “blanks” on problem sections of the route 1 p.m. 100 l.m. 50 000
4.3. Installation of racks and cabinets 1 rack 1 rack 8 000
4.4. Additional work related to laying cables throughout the building (with materials) 1 object 1 object 20 000
5. LAYING AND INSTALLATION OF FIBER OPTICAL CABLE USING THE VKP METHOD (EXCLUDING THE COST OF THE CABLE)
5.1. Laying and installation of 8-fiber optical cable using the VCP method 1 km 0.1 km 180 000
5.2. Laying and installation of 16-fiber optical cable using the VCP method 1 km 0.1 km 190 000
6. COST OF MATERIALS NOT INCLUDED IN PRICES FOR WORK
6.1. 8-fiber optical cable in standard sheath 1 km 36 400
6.2. 8-fiber optical cable in a flame retardant sheath when laid in groups 1 km 49 600
6.3. 16-fiber optical cable in standard sheath 1 km 41 800
6.4. 16-fiber cable in a flame retardant sheath when laid in groups 1 km 55 000
6.5. 24-fiber optical cable in standard sheath 1 km 49 000
6.6. 24-fiber optical cable in a flame retardant sheath when laid in groups 1 km 64 000
6.7. 32-fiber optical cable in standard sheath 1 km 55 900
6.8. 32-fiber optical cable in a flame retardant sheath when laid in groups 1 km 69 100
6.9. 48-fiber optical cable in a standard sheath 1 km 69 000
6.10. 48-fiber optical cable in a flame retardant sheath when laid in groups 1 km 82 200
6.11. 64-fiber optical cable in a standard sheath 1 km 95 100
6.12. 64-fiber optical cable in a flame retardant sheath when laid in groups 1 km 110 900
6.13. 96-fiber optical cable in standard sheath 1 km 127 100
6.14. 96-fiber optical cable in a flame retardant sheath when laid in groups 1 km 142 900
6.15. 144-fiber optical cable in a standard sheath 1 km 175 600
6.16. 144-fiber optical cable in a flame retardant sheath when laid in groups 1 km 191 500
6.17. 288-fiber optical cable in a standard sheath 1 km 355 100
6.18. 288-fiber optical cable in a flame retardant sheath when laid in groups 1 km 374 000
6.19. MOG branching coupling (for mounting from 8 to 48 optical fibers) 1 set 2 800
6.20. MOG branching coupling (for mounting from 49 to 96 optical fibers) 1 set 3 100
6.21. Branch coupling MTok-G3/216-1KT3645-K 1 set 10 200
6.22. Branching coupling MTok-G4/480-10K4845-K 1 set 16 300
7. Additional costs
7.1. Payment for: issuance of a permit, technical supervision of work in the LCS of PJSC MGTS, PJSC Rostelecom, access to external inspection of cable structures and communication cables. 1 piece 1 piece 12 000

 

Note:

1. If it is necessary to perform construction and installation work:

at night, on weekends, a coefficient of 1.3 is applied;

up to 15 calendar days, a coefficient of 1.3 is applied;

up to 10 calendar days, a coefficient of 1.5 is applied.

Particularly urgent work (up to 3 working days) - coefficient 1.8.

2. In the case of dismantling cables, cabinets, racks, wells, the cost of work is determined at the rate of 50% of the cost of construction and installation work, excluding the cost of materials.

3. For additional types of work not provided for in this Appendix, the price is determined by the estimate approved by the Parties.